FAST-41 Eligibility
FAST-41 offers many benefits to project developers and optimizes the permitting process so that infrastructure developers get a permitting decision in a timely manner.
Participation in the FAST-41 program is voluntary. Sponsors of infrastructure projects that meet FAST-41’s eligibility criteria must request coverage to obtain program benefits by submitting a FAST-41 Initiation Notice (FIN). When submitting a FIN, a project sponsor must show that the project meets FAST-41 eligibility requirements, which are listed below.
FAST-41 Eligibility Requirements
FIRST — the project must be in one of the following industry sectors:
Renewable energy production
Conventional energy production
Electricity transmission
Surface transportation
Aviation
Ports and waterways
Water resource projects
Broadband
Pipelines
Manufacturing
Semiconductors
Artificial intelligence and machine learning
High-performance computing, advanced computer hardware and software
Quantum information science and technology
Data storage and data management
Cybersecurity
Carbon capture
Energy storage
Mining
SECOND – The project must meet the criteria in one of the four pathways to becoming a Covered Project listed below:
Standard Pathway
Project is subject to the National Environmental Policy Act (NEPA)
Project is likely to require a total investment of more than $200,000,000
Project does not qualify for “abbreviated authorization or environmental review processes” under any applicable law
Discretionary Pathway
Project is subject to NEPA
Project is of a size and complexity that makes it, in the opinion of the Permitting Council, likely to benefit from enhanced oversight and coordination, including (but not limited to) a project likely to require:
Authorization from or environmental review involving more than two Federal agencies; or
The preparation of an environmental impact statement (EIS) under NEPA.
Tribal Sponsored Pathway
Project is subject to NEPA
Project is sponsored by an Indian Tribe, an Alaska Native Corporation, a Native Hawaiian Organization (as defined in section 7517 of title 20), the Department of Hawaiian Home Lands, or the
Office of Hawaiian AffairsProject is located on land owned or under the jurisdiction of the entity that sponsors the activity
Projects submitting a FIN based on the Tribal sponsored pathway are exempt from “abbreviated authorization or environmental review” limitation and from the $200 million threshold in the standard pathway
Carbon Capture Pathway
Construction of infrastructure for “carbon capture” includes construction of:
Any facility, technology, or system that captures, utilizes, or sequesters carbon dioxide emissions, including projects for direct air capture
Carbon dioxide pipelines
Criteria:
Project is covered by a programmatic plan or environmental review developed for the primary purpose of facilitating development of carbon dioxide pipelines
Projects submitting a FIN based on the carbon capture pathway are exempt from the “subject to NEPA” requirement that applies in all other categories.
THIRD – Project sponsors must request FAST-41 coverage:
To become a FAST-41 covered project, sponsors need to submit a FAST-41 Initiation Notice (FIN) with basic information about the project using either an online FIN submission tool or via email:
Request FAST-41 coverage through online FIN submission tool
Request FAST-41 coverage via email submission
Last Updated: Wednesday, December 11, 2024